Construction; building costs, building phase, type of building

Construction; building costs, building phase, type of building

Type of building Building phase Periods Building costs (mln euro)
Halls and warehouses Orders received by contractors 2024 2nd quarter* 757
Halls and warehouses Building projects started 2024 2nd quarter* 570
Halls and warehouses Building projects not yet started 2024 2nd quarter* 482
Halls and warehouses Building projects under construction 2024 2nd quarter* 2,185
Halls and warehouses Production of building projects 2024 2nd quarter* 375
Halls and warehouses Remaining production of buildings 2024 2nd quarter* 1,163
Halls and warehouses Building projects completed 2024 2nd quarter* 293
Glasshouses Orders received by contractors 2024 2nd quarter* 19
Glasshouses Building projects started 2024 2nd quarter* 42
Glasshouses Building projects not yet started 2024 2nd quarter* 16
Glasshouses Building projects under construction 2024 2nd quarter* 80
Glasshouses Production of building projects 2024 2nd quarter* 16
Glasshouses Remaining production of buildings 2024 2nd quarter* 53
Glasshouses Building projects completed 2024 2nd quarter* 6
Source: https://statflow/Statweb/publication/?VW=T&DM=PREVIEW&PA=83705ENG&D1=0&D2=a&D3=a&D4=141-160&HD=240820-1519&LA=EN&HDR=T,G2&STB=G1,G3
Explanation of symbols

Table explanation


This table shows the value (expressed in building costs) of the construction of building projects expected shortly. It also shows the value of the actually realised monthly production of building projects. The figures relate to building projects with building costs of 50 thousand euro or more. The total building costs are broken down into building costs by building phase and by type of building.

Data available from: January 2015.

Status of the figures:
Figures of the latest 12 months are provisional.
Municipalities with non-response are estimated. The later received response of municipalities over previous periods have been processed in the figures of the month in which the building permit was granted. As a result, figures about the same month may vary over time. Twelve months after publication the provisional figures become definite.

Changes as of August 30, 2024:
The figures of June and the second quarter of 2024 have been added and all figures as of June 2023 may be revised.

When will new figures be published?
The new figures will be published on the last working day of the second month after the reporting month. The figures for the same reporting month of a year earlier then become final.

Description topics

Building costs
Estimated construction costs for all buildings for which a building permit of more than 50 thousand euros has been granted, excluding VAT.