Construction; building costs, building phase, type of building

Construction; building costs, building phase, type of building

Type of building Building phase Periods Building costs (mln euro)
Total buildings Orders received by contractors 2024 2nd quarter* 6,499
Total buildings Building projects started 2024 2nd quarter* 6,560
Total buildings Building projects not yet started 2024 2nd quarter* 3,834
Total buildings Building projects under construction 2024 2nd quarter* 34,730
Total buildings Production of building projects 2024 2nd quarter* 5,455
Total buildings Remaining production of buildings 2024 2nd quarter* 17,678
Total buildings Building projects completed 2024 2nd quarter* 5,191
Dwellings Orders received by contractors 2024 2nd quarter* 3,952
Dwellings Building projects started 2024 2nd quarter* 4,408
Dwellings Building projects not yet started 2024 2nd quarter* 1,912
Dwellings Building projects under construction 2024 2nd quarter* 22,976
Dwellings Production of building projects 2024 2nd quarter* 3,523
Dwellings Remaining production of buildings 2024 2nd quarter* 11,691
Dwellings Building projects completed 2024 2nd quarter* 3,351
Offices Orders received by contractors 2024 2nd quarter* 111
Offices Building projects started 2024 2nd quarter* 102
Offices Building projects not yet started 2024 2nd quarter* 114
Offices Building projects under construction 2024 2nd quarter* 1,209
Offices Production of building projects 2024 2nd quarter* 161
Offices Remaining production of buildings 2024 2nd quarter* 576
Offices Building projects completed 2024 2nd quarter* 116
Combined company halls Orders received by contractors 2024 2nd quarter* 695
Combined company halls Building projects started 2024 2nd quarter* 631
Combined company halls Building projects not yet started 2024 2nd quarter* 347
Combined company halls Building projects under construction 2024 2nd quarter* 3,426
Combined company halls Production of building projects 2024 2nd quarter* 547
Combined company halls Remaining production of buildings 2024 2nd quarter* 1,703
Combined company halls Building projects completed 2024 2nd quarter* 585
Halls and warehouses Orders received by contractors 2024 2nd quarter* 757
Halls and warehouses Building projects started 2024 2nd quarter* 570
Halls and warehouses Building projects not yet started 2024 2nd quarter* 482
Halls and warehouses Building projects under construction 2024 2nd quarter* 2,185
Halls and warehouses Production of building projects 2024 2nd quarter* 375
Halls and warehouses Remaining production of buildings 2024 2nd quarter* 1,163
Halls and warehouses Building projects completed 2024 2nd quarter* 293
Glasshouses Orders received by contractors 2024 2nd quarter* 19
Glasshouses Building projects started 2024 2nd quarter* 42
Glasshouses Building projects not yet started 2024 2nd quarter* 16
Glasshouses Building projects under construction 2024 2nd quarter* 80
Glasshouses Production of building projects 2024 2nd quarter* 16
Glasshouses Remaining production of buildings 2024 2nd quarter* 53
Glasshouses Building projects completed 2024 2nd quarter* 6
Agricultural sheds and stables Orders received by contractors 2024 2nd quarter* 95
Agricultural sheds and stables Building projects started 2024 2nd quarter* 109
Agricultural sheds and stables Building projects not yet started 2024 2nd quarter* 84
Agricultural sheds and stables Building projects under construction 2024 2nd quarter* 238
Agricultural sheds and stables Production of building projects 2024 2nd quarter* 86
Agricultural sheds and stables Remaining production of buildings 2024 2nd quarter* 129
Agricultural sheds and stables Building projects completed 2024 2nd quarter* 79
Shops Orders received by contractors 2024 2nd quarter* 40
Shops Building projects started 2024 2nd quarter* 32
Shops Building projects not yet started 2024 2nd quarter* 33
Shops Building projects under construction 2024 2nd quarter* 234
Shops Production of building projects 2024 2nd quarter* 51
Shops Remaining production of buildings 2024 2nd quarter* 97
Shops Building projects completed 2024 2nd quarter* 56
Schools Orders received by contractors 2024 2nd quarter* 131
Schools Building projects started 2024 2nd quarter* 175
Schools Building projects not yet started 2024 2nd quarter* 126
Schools Building projects under construction 2024 2nd quarter* 1,196
Schools Production of building projects 2024 2nd quarter* 191
Schools Remaining production of buildings 2024 2nd quarter* 639
Schools Building projects completed 2024 2nd quarter* 185
Other buildings Orders received by contractors 2024 2nd quarter* 700
Other buildings Building projects started 2024 2nd quarter* 492
Other buildings Building projects not yet started 2024 2nd quarter* 719
Other buildings Building projects under construction 2024 2nd quarter* 3,187
Other buildings Production of building projects 2024 2nd quarter* 504
Other buildings Remaining production of buildings 2024 2nd quarter* 1,627
Other buildings Building projects completed 2024 2nd quarter* 520
Source: https://statflow/Statweb/publication/?VW=T&DM=PREVIEW&PA=83705ENG&D1=0&D2=a&D3=a&D4=141-160&HD=240820-1519&LA=EN&HDR=T,G2&STB=G1,G3
Explanation of symbols

Table explanation


This table shows the value (expressed in building costs) of the construction of building projects expected shortly. It also shows the value of the actually realised monthly production of building projects. The figures relate to building projects with building costs of 50 thousand euro or more. The total building costs are broken down into building costs by building phase and by type of building.

Data available from: January 2015.

Status of the figures:
Figures of the latest 12 months are provisional.
Municipalities with non-response are estimated. The later received response of municipalities over previous periods have been processed in the figures of the month in which the building permit was granted. As a result, figures about the same month may vary over time. Twelve months after publication the provisional figures become definite.

Changes as of August 30, 2024:
The figures of June and the second quarter of 2024 have been added and all figures as of June 2023 may be revised.

When will new figures be published?
The new figures will be published on the last working day of the second month after the reporting month. The figures for the same reporting month of a year earlier then become final.

Description topics

Building costs
Estimated construction costs for all buildings for which a building permit of more than 50 thousand euros has been granted, excluding VAT.