Construction; building costs, building phase, type of building

Construction; building costs, building phase, type of building

Type of building Building phase Periods Building costs (mln euro)
Total buildings Orders received by contractors 2023 1st quarter 4,936
Total buildings Orders received by contractors 2023 April 1,873
Total buildings Orders received by contractors 2023 May* 1,494
Total buildings Orders received by contractors 2023 June* 1,899
Total buildings Orders received by contractors 2023 2nd quarter* 5,266
Total buildings Orders received by contractors 2023 July* 1,522
Total buildings Orders received by contractors 2023 August* 1,295
Total buildings Orders received by contractors 2023 September* 1,394
Total buildings Orders received by contractors 2023 3rd quarter* 4,211
Total buildings Orders received by contractors 2023 October* 2,044
Total buildings Orders received by contractors 2023 November* 1,562
Total buildings Orders received by contractors 2023 December* 1,674
Total buildings Orders received by contractors 2023 4th quarter* 5,280
Total buildings Orders received by contractors 2023* 19,694
Total buildings Orders received by contractors 2024 January* 1,208
Total buildings Orders received by contractors 2024 February* 1,888
Total buildings Orders received by contractors 2024 March* 2,388
Total buildings Orders received by contractors 2024 1st quarter* 5,484
Total buildings Orders received by contractors 2024 April* 2,440
Dwellings Orders received by contractors 2023 1st quarter 2,850
Dwellings Orders received by contractors 2023 April 1,235
Dwellings Orders received by contractors 2023 May* 904
Dwellings Orders received by contractors 2023 June* 1,265
Dwellings Orders received by contractors 2023 2nd quarter* 3,404
Dwellings Orders received by contractors 2023 July* 1,010
Dwellings Orders received by contractors 2023 August* 739
Dwellings Orders received by contractors 2023 September* 1,000
Dwellings Orders received by contractors 2023 3rd quarter* 2,749
Dwellings Orders received by contractors 2023 October* 1,366
Dwellings Orders received by contractors 2023 November* 1,021
Dwellings Orders received by contractors 2023 December* 867
Dwellings Orders received by contractors 2023 4th quarter* 3,253
Dwellings Orders received by contractors 2023* 12,256
Dwellings Orders received by contractors 2024 January* 726
Dwellings Orders received by contractors 2024 February* 1,366
Dwellings Orders received by contractors 2024 March* 1,650
Dwellings Orders received by contractors 2024 1st quarter* 3,742
Dwellings Orders received by contractors 2024 April* 1,372
Offices Orders received by contractors 2023 1st quarter 201
Offices Orders received by contractors 2023 April 47
Offices Orders received by contractors 2023 May* 32
Offices Orders received by contractors 2023 June* 77
Offices Orders received by contractors 2023 2nd quarter* 156
Offices Orders received by contractors 2023 July* 43
Offices Orders received by contractors 2023 August* 86
Offices Orders received by contractors 2023 September* 14
Offices Orders received by contractors 2023 3rd quarter* 143
Offices Orders received by contractors 2023 October* 88
Offices Orders received by contractors 2023 November* 78
Offices Orders received by contractors 2023 December* 36
Offices Orders received by contractors 2023 4th quarter* 202
Offices Orders received by contractors 2023* 702
Offices Orders received by contractors 2024 January* 41
Offices Orders received by contractors 2024 February* 22
Offices Orders received by contractors 2024 March* 59
Offices Orders received by contractors 2024 1st quarter* 122
Offices Orders received by contractors 2024 April* 23
Combined company halls Orders received by contractors 2023 1st quarter 662
Combined company halls Orders received by contractors 2023 April 215
Combined company halls Orders received by contractors 2023 May* 148
Combined company halls Orders received by contractors 2023 June* 98
Combined company halls Orders received by contractors 2023 2nd quarter* 462
Combined company halls Orders received by contractors 2023 July* 101
Combined company halls Orders received by contractors 2023 August* 92
Combined company halls Orders received by contractors 2023 September* 97
Combined company halls Orders received by contractors 2023 3rd quarter* 290
Combined company halls Orders received by contractors 2023 October* 111
Combined company halls Orders received by contractors 2023 November* 179
Combined company halls Orders received by contractors 2023 December* 287
Combined company halls Orders received by contractors 2023 4th quarter* 577
Combined company halls Orders received by contractors 2023* 1,991
Combined company halls Orders received by contractors 2024 January* 116
Combined company halls Orders received by contractors 2024 February* 116
Combined company halls Orders received by contractors 2024 March* 143
Combined company halls Orders received by contractors 2024 1st quarter* 375
Combined company halls Orders received by contractors 2024 April* 375
Halls and warehouses Orders received by contractors 2023 1st quarter 462
Halls and warehouses Orders received by contractors 2023 April 143
Halls and warehouses Orders received by contractors 2023 May* 222
Halls and warehouses Orders received by contractors 2023 June* 135
Halls and warehouses Orders received by contractors 2023 2nd quarter* 500
Halls and warehouses Orders received by contractors 2023 July* 111
Halls and warehouses Orders received by contractors 2023 August* 104
Halls and warehouses Orders received by contractors 2023 September* 68
Halls and warehouses Orders received by contractors 2023 3rd quarter* 283
Halls and warehouses Orders received by contractors 2023 October* 88
Halls and warehouses Orders received by contractors 2023 November* 65
Halls and warehouses Orders received by contractors 2023 December* 154
Halls and warehouses Orders received by contractors 2023 4th quarter* 306
Halls and warehouses Orders received by contractors 2023* 1,551
Halls and warehouses Orders received by contractors 2024 January* 119
Halls and warehouses Orders received by contractors 2024 February* 89
Halls and warehouses Orders received by contractors 2024 March* 184
Halls and warehouses Orders received by contractors 2024 1st quarter* 392
Halls and warehouses Orders received by contractors 2024 April* 320
Glasshouses Orders received by contractors 2023 1st quarter 5
Glasshouses Orders received by contractors 2023 April 1
Glasshouses Orders received by contractors 2023 May* 2
Glasshouses Orders received by contractors 2023 June* 1
Glasshouses Orders received by contractors 2023 2nd quarter* 4
Glasshouses Orders received by contractors 2023 July* 5
Glasshouses Orders received by contractors 2023 August* 5
Glasshouses Orders received by contractors 2023 September* 5
Glasshouses Orders received by contractors 2023 3rd quarter* 14
Glasshouses Orders received by contractors 2023 October* 4
Glasshouses Orders received by contractors 2023 November* 19
Glasshouses Orders received by contractors 2023 December* 7
Glasshouses Orders received by contractors 2023 4th quarter* 30
Glasshouses Orders received by contractors 2023* 53
Glasshouses Orders received by contractors 2024 January* 0
Glasshouses Orders received by contractors 2024 February* 5
Glasshouses Orders received by contractors 2024 March* 34
Glasshouses Orders received by contractors 2024 1st quarter* 39
Glasshouses Orders received by contractors 2024 April* 4
Agricultural sheds and stables Orders received by contractors 2023 1st quarter 67
Agricultural sheds and stables Orders received by contractors 2023 April 24
Agricultural sheds and stables Orders received by contractors 2023 May* 25
Agricultural sheds and stables Orders received by contractors 2023 June* 27
Agricultural sheds and stables Orders received by contractors 2023 2nd quarter* 76
Agricultural sheds and stables Orders received by contractors 2023 July* 29
Agricultural sheds and stables Orders received by contractors 2023 August* 17
Agricultural sheds and stables Orders received by contractors 2023 September* 24
Agricultural sheds and stables Orders received by contractors 2023 3rd quarter* 70
Agricultural sheds and stables Orders received by contractors 2023 October* 25
Agricultural sheds and stables Orders received by contractors 2023 November* 38
Agricultural sheds and stables Orders received by contractors 2023 December* 21
Agricultural sheds and stables Orders received by contractors 2023 4th quarter* 84
Agricultural sheds and stables Orders received by contractors 2023* 298
Agricultural sheds and stables Orders received by contractors 2024 January* 29
Agricultural sheds and stables Orders received by contractors 2024 February* 39
Agricultural sheds and stables Orders received by contractors 2024 March* 38
Agricultural sheds and stables Orders received by contractors 2024 1st quarter* 107
Agricultural sheds and stables Orders received by contractors 2024 April* 37
Shops Orders received by contractors 2023 1st quarter 30
Shops Orders received by contractors 2023 April 12
Shops Orders received by contractors 2023 May* 6
Shops Orders received by contractors 2023 June* 15
Shops Orders received by contractors 2023 2nd quarter* 32
Shops Orders received by contractors 2023 July* 8
Shops Orders received by contractors 2023 August* 27
Shops Orders received by contractors 2023 September* 22
Shops Orders received by contractors 2023 3rd quarter* 56
Shops Orders received by contractors 2023 October* 15
Shops Orders received by contractors 2023 November* 13
Shops Orders received by contractors 2023 December* 21
Shops Orders received by contractors 2023 4th quarter* 49
Shops Orders received by contractors 2023* 167
Shops Orders received by contractors 2024 January* 9
Shops Orders received by contractors 2024 February* 15
Shops Orders received by contractors 2024 March* 7
Shops Orders received by contractors 2024 1st quarter* 31
Shops Orders received by contractors 2024 April* 20
Schools Orders received by contractors 2023 1st quarter 227
Schools Orders received by contractors 2023 April 56
Schools Orders received by contractors 2023 May* 47
Schools Orders received by contractors 2023 June* 33
Schools Orders received by contractors 2023 2nd quarter* 136
Schools Orders received by contractors 2023 July* 64
Schools Orders received by contractors 2023 August* 87
Schools Orders received by contractors 2023 September* 35
Schools Orders received by contractors 2023 3rd quarter* 186
Schools Orders received by contractors 2023 October* 58
Schools Orders received by contractors 2023 November* 34
Schools Orders received by contractors 2023 December* 115
Schools Orders received by contractors 2023 4th quarter* 207
Schools Orders received by contractors 2023* 756
Schools Orders received by contractors 2024 January* 50
Schools Orders received by contractors 2024 February* 60
Schools Orders received by contractors 2024 March* 60
Schools Orders received by contractors 2024 1st quarter* 170
Schools Orders received by contractors 2024 April* 60
Other buildings Orders received by contractors 2023 1st quarter 432
Other buildings Orders received by contractors 2023 April 140
Other buildings Orders received by contractors 2023 May* 108
Other buildings Orders received by contractors 2023 June* 247
Other buildings Orders received by contractors 2023 2nd quarter* 495
Other buildings Orders received by contractors 2023 July* 151
Other buildings Orders received by contractors 2023 August* 139
Other buildings Orders received by contractors 2023 September* 130
Other buildings Orders received by contractors 2023 3rd quarter* 420
Other buildings Orders received by contractors 2023 October* 288
Other buildings Orders received by contractors 2023 November* 114
Other buildings Orders received by contractors 2023 December* 169
Other buildings Orders received by contractors 2023 4th quarter* 571
Other buildings Orders received by contractors 2023* 1,919
Other buildings Orders received by contractors 2024 January* 119
Other buildings Orders received by contractors 2024 February* 175
Other buildings Orders received by contractors 2024 March* 213
Other buildings Orders received by contractors 2024 1st quarter* 507
Other buildings Orders received by contractors 2024 April* 230
Source: CBS.
Explanation of symbols

Dataset is not available.


This table shows the value (expressed in building costs) of the construction of building projects expected shortly. It also shows the value of the actually realised monthly production of building projects. The figures relate to building projects with building costs of 50 thousand euro or more. The total building costs are broken down into building costs by building phase and by type of building.

Data available from: January 2015.

Status of the figures:
Figures of the latest 12 months are provisional.
Municipalities with non-response are estimated. The later received response of municipalities over previous periods have been processed in the figures of the month in which the building permit was granted. As a result, figures about the same month may vary over time. Twelve months after publication the provisional figures become definite.

Changes as of June 28, 2024:
The figures of April 2024 have been added and all figures as of April 2023 may be revised.

When will new figures be published?
The new figures will be published on the last working day of the second month after the reporting month. The figures for the same reporting month of a year earlier then become final.

Description topics

Building costs
Estimated construction costs for all buildings for which a building permit of more than 50 thousand euros has been granted, excluding VAT.